Weekly Construction Update (47)
Posted by: admin on September 16, 2011, No Comments
Following is a summary of the planned construction activity for the week of September 19, 2011
New Student Housing Project: – (Project Manager – Tom Bartek tbartek@esu.edu Tel: 3038)
Work for both buildings is progressing well within the recovery schedule and the envelope system is 98% complete for Building ‘A’ and 90% complete for Building ‘B’. Installation of exterior louvers for the attic mechanical rooms and exterior site work including finish grading and concrete work for sidewalks and patios has started and progressing well. Installation of Mechanical, Electrical, Plumbing and Fire Suppression Systems and installation of interior finishes including casework, countertops and flooring material are continuing.
Expected Impact: Minor traffic flow interruption may occur along Isabelle Street to continue street work improvements for concrete curb adjacent to the existing sidewalks and to create a new two-way vehicle entrance into the new Hawthorn parking lot (currently under construction and opening in November). In addition, the asphalt walkway north of Dansbury Common, from Green Street to Isabelle Street will remain closed for underground steam line removal and replacement and is anticipated to be completed 1 October 2011 for pressure testing.
Monroe Hall Renovation Project: – (Project Manager – John Bloshinski II jbloshinski@esu.edu Tel: 3631)
In the Quad; geo-thermal well drilling is now complete and horizontal piping will be installed linking wells. At the south side of the building; underpinning the existing footing will continue, as well as, preparation for the elevator addition footings. Abatement continues in the building; third and ground floors are complete and second floor is expected to be completed Wednesday. Abatement work will begin on the first floor once the second floor is cleared.
Expected Impact: Noise from backhoes installing horizontal piping and demolition activity.
Marguerite St. Parking Lot:– (Project Manager – John Bloshinski II jbloshinski@esu.edu Tel: 3631)
Work continues on the site across from the existing parking lot on Gwendolyn Street to create an additional parking lot for 102 cars. Work will continue on the storm water infiltration/detention system.
Expected Impact: Noise, movement of construction vehicle around the site and possible dust.
Caution: You are requested to remain outside all construction fenced–in areas (especially around the New Student Housing and Monroe Hall Projects) and be alert to slow moving construction vehicles exiting and entering the sites. Please observe all construction rerouting signs and for you safety, we urge you not to walk behind parked vehicles along the north side of Normal Street and to use the south side walk along Normal Street adjacent to the Koehler Field House.
Search
Recent Posts
ESU Expands Criminal Justice Internships to Include Educational Safety
December 11, 2024 - Read more